面向大规模定制的瓶颈成组调度启发式方法研究

陈亚绒1,2;管在林1;彭运芳1;邵新宇1
  

  1. 1.华中科技大学数字制造装备与技术国家重点实验室,武汉,430074
    2.温州大学,温州,325035
  • 出版日期:2010-04-25 发布日期:2010-05-05
  • 基金资助:
    国家863高技术研究发展计划资助项目(2007AA04Z110);国家自然科学基金资助项目(70772056);国家杰出青年科学基金资助项目(50675082);浙江省教育厅资助项目(Y200701470);温州市科技计划资助项目(G20090038) 
    National High-tech R&D Program of China (863 Program) (No. 2007AA04Z110);
    National Natural Science Foundation of China(No. 70772056);
    National Science Funds for Distinguished Young Scholars( No. 50675082);
    Zhejiang Provincial Program of Ministry of Education of China(No. Y200701470);
    Science and Technology Program of Wenzhou ( No. G20090038)

Research on Bottleneck Group Scheduling Heuristics for Mass Customization

Chen Yarong1,2;Guan Zailin1;Peng Yunfang1;Shao Xinyu1
  

  1. 1.State Key Laboratory of Digital Manufacturing Equipment & Technology,Huazhong University of Science and Technology,Wuhan,430074
    2.Wenzhou University,Wenzhou,Zhejiang,325035
  • Online:2010-04-25 Published:2010-05-05
  • Supported by:
     
    National High-tech R&D Program of China (863 Program) (No. 2007AA04Z110);
    National Natural Science Foundation of China(No. 70772056);
    National Science Funds for Distinguished Young Scholars( No. 50675082);
    Zhejiang Provincial Program of Ministry of Education of China(No. Y200701470);
    Science and Technology Program of Wenzhou ( No. G20090038)

摘要:

基于对大规模定制生产模式的产品与生产特征的分析,描述了面向大规模定制的模块工件成组调度问题,提出了以识别瓶颈工序为基础的最小化加权拖期成组调度启发式方法,实现了生产成本与交货期的优化。实际生产数据的调度结果表明,与模块单批调度和完全批成组调度方法相比较,基于瓶颈的最小化加权拖期模块成组调度启发式方法更可行、更有效。

关键词:

Abstract:

By analyzing the characteristics of products and the production in mass customization,we discussed the modular group scheduling problem,and presented a heuristic method for minimizing the weighted tardiness.The method involved the identification of bottleneck operation,and the optimization of both of the production cost and the delivery performance.The results of practice data of an assemble enterprise show,as compared to the modular single scheduling and modular fully-group scheduling,the method presented herein is more feasible and effective.

Key words: